Impediments: finding them, logging them, removing them

By Scrumagic Team Last reviewed 6 min read

In short

An impediment is anything that slows the team down and that the team cannot fix on its own. Scrum makes them visible through the board and the Daily Scrum, and the Scrum Master is accountable for causing their removal. A written log, kept in public, turns a vague sense that things are slow into a short list of named problems with owners and dates.

"We're waiting on access." It is said in the Daily Scrum on Tuesday, and again on Wednesday, and on Thursday it is simply part of the furniture. Nobody has been negligent. Everyone assumed someone else was dealing with it. An impediment log exists to stop that sentence being said three days running.

What counts

The SBOK® Guide defines an impediment as any hindrance or hurdle that reduces the productivity of the Scrum Team. It says impediments must be identified, resolved and removed if the team is to keep working effectively, and that failing to do so can be very costly. They may be internal, such as an inefficient workflow or poor communication, or external, with software licence problems and unnecessary documentation requirements as its examples.

The Scrum Guide does not define the word, but it uses it in the same way. The Daily Scrum improves communication and identifies impediments, and the Scrum Master serves the team by causing the removal of impediments to its progress. The phrase "causing the removal" is deliberate. The Scrum Master does not have to fix every impediment personally. They have to make sure it gets fixed.

A practical test: is the team unable to resolve it by itself? A Developer who needs to ask a colleague a question has a conversation, not an impediment. A Developer who cannot proceed without a decision, an access right, a purchase or a change from another department has an impediment.

Where they come from

Impediments cluster into a few families.

  • Access and environments. No test environment, an expired certificate, a missing account.
  • Decisions. An answer only the Product Owner or a stakeholder can give, and it has not come.
  • Dependencies. Another team or a vendor holds something the work needs. See stories, tasks and dependencies.
  • Process and interruptions. Meetings outside Scrum, requests that bypass the Product Owner, unnecessary approvals.
  • Skills and knowledge. Only one person can do a task, or nobody can.
  • The team itself. A recurring friction, unclear working agreements, low morale.

The SBOK points out that the transparency inherent in Scrum makes impediments quick to spot, which is the point of the board and the daily meeting.

How to find them early

  • At the Daily Scrum. The SBOK's version of the meeting asks about impediments directly. The Scrum Guide's version leaves the format to the Developers, but says it identifies impediments. Either way, listen for the word "waiting" or "still".
  • On the board. A task that has not moved for two days is a prompt to ask why.
  • In the Retrospective. The slower, structural impediments appear here. See the Retrospective.
  • At the Sprint Review. The SBOK says impediments should be discussed in the Sprint Review as appropriate, because stakeholders are often part of the cause.
  • By watching. A Scrum Master who attends the events and listens will hear problems before they are named.

The log

The SBOK has the Scrum Master record impediments formally in an impediment log, to be discussed at the Daily Standup and Sprint Review meetings as appropriate. The Scrum Guide does not name a log, but it asks for transparency, and a visible list is the simplest form of it.

A log can be a section of the board, a shared document or a column in a tool. What matters is what it contains:

Field Why it is there
What is blocked In one sentence, in the team's words
Who it affects Names or stories, so the cost is clear
Date raised So its age can be seen
Owner One person who is making sure it moves
Next step and date What will happen, and by when
Status Open, escalated, resolved

Two habits keep it alive. Review it at every Daily Scrum, briefly, and review its age. And close items explicitly: "resolved on Thursday, by the platform team" is a small piece of evidence that raising problems works.

Who removes it

Under the Guide, the Scrum Master is accountable for causing the removal. In practice there are three routes.

  1. The team solves it. Some impediments feel external and are not. A short conversation or a small change in how the team works is enough.
  2. The Scrum Master solves it. Chasing an approval, arranging access, having a word with someone who is interrupting the team.
  3. It is escalated. When the cause sits with management, another department or a vendor, the Scrum Master takes it up the line. The SBOK says that when required, the Scrum Master can escalate external issues and impediments to management for resolution or removal.

A useful rule is to ask for the decision, not for sympathy. "We need a test environment by Thursday or the payment story will not make the Sprint" can be answered. "We are having environment problems" cannot.

A worked example

An invented case. On day two, a Developer reports that the payment provider's test account has not been approved. The Scrum Master adds it to the log, names itself as owner, and records the cost: the payment story depends on it.

  • Day two. The Scrum Master contacts the person who can approve and asks for a date.
  • Day three. No reply. The Daily Scrum notes the item has not moved, and the team agrees to build against a stub in the meantime.
  • Day four. The Scrum Master escalates to the sponsor's office with a single sentence about the date at risk.
  • Day five. The account is approved. The log records it as resolved, and the team swaps the stub for the real thing.

Two things made the difference: the item was written down with an owner, and the team found a workaround that kept the goal alive while the impediment was being removed.

Common mistakes

  • Treating every difficulty as an impediment. A log of forty items buries the three that matter.
  • No owner. An item everyone knows about is not being handled.
  • A log nobody reads. If it is not visited at the Daily Scrum, it is a graveyard.
  • The Scrum Master hides problems from the stakeholders. Transparency applies upward too.
  • Escalating with no ask. A report without a request gives the manager nothing to do.
  • Working around the same blocker repeatedly. A workaround that becomes permanent is a debt. The Retrospective should ask why the cause was never removed.

The Agile Manifesto principle that the team regularly reflects on how to become more effective, then tunes and adjusts its behaviour, is the other half of dealing with impediments: fix this one, then ask what produced it.

Two perspectives

The Scrum Guide and SBOK agree here.

Scrum Guide

The Scrum Guide has the Scrum Master cause the removal of impediments to the team's progress, and says the Daily Scrum improves communication and identifies impediments.

SBOK®

The SBOK® Guide defines an impediment as any hindrance that reduces the team's productivity, internal or external, and has the Scrum Master record them formally in an impediment log discussed at Daily Standup and Sprint Review meetings, with escalation to management when needed.

Same thing, different words

  • Impediment (Scrum Guide) = Impediment (SBOK)

Both sources give the Scrum Master the job of making sure impediments are removed. The log is the SBOK's tool, and a team following the Guide can use any visible list.

How to practise it

In the simulator, impediments surface on the board and at the daily standup, and you decide whether to clear them, log them and carry on, or leave them to the team. Each choice has consequences that carry forward into later Sprints.

Sources

  1. The 2020 Scrum Guide, Scrum Guides. Read on 13 October 2026.
  2. Principles behind the Agile Manifesto, Agile Manifesto. Read on 13 October 2026.

SBOK® is a registered trademark of its owner. Scrumagic is independent and is not affiliated with the owners of SBOK®.

Share this post Link copied

Nothing opened? This computer may have no email program set up. Write it in Gmail or use the copy button and paste the link into your email.

  • Learn Scrum 7 min read

    From stories to tasks: decomposition, dependencies and hours

    After choosing the Sprint's stories, the team plans how to build them by breaking each into tasks of a day or less and noting what waits on what. Estimating tasks in hours is optional. The Scrum Guide calls the result the plan part of the Sprint Backlog, left to the Developers. The SBOK splits it into two processes, one optional.

  • Learn Scrum 6 min read

    Retrospective actions that actually happen

    Most retrospectives produce a good discussion and a list of intentions, and then nothing changes. Actions get done when there are few of them, when each one is small and specific, when someone owns it with a date, and when it sits in the Sprint Backlog as real work. The follow-up at the next retrospective is what keeps the habit alive.

  • Learn Scrum 6 min read

    The purpose of the Sprint Retrospective

    The Sprint Retrospective is the team's regular chance to inspect how it worked, not what it built, and to choose changes that raise quality and effectiveness. It ends the Sprint, it is for the Scrum Team alone, and its measure is whether something is different in the next Sprint. A retrospective that produces a list but no change has failed, however pleasant the discussion.

  • Learn Scrum 7 min read

    The Scrum Master role: what they do on a normal Tuesday

    The Scrum Master is accountable for establishing Scrum and for the team's effectiveness. In practice that means teaching, coaching, removing obstacles and protecting the events, for the team, the Product Owner and the wider organisation. The Scrum Master has no authority over the work itself, which is why the role depends on influence, not instruction.

  • Learn Scrum 7 min read

    Project vision and Product Goal: pointing the work somewhere

    A vision says why the work exists and where it is heading, in a few sentences that everyone on the team can repeat. The Scrum Guide calls the long-term version the Product Goal. The SBOK builds a Project Vision Statement from the business case at the very start of a project. Both ask for the same thing: focus on the problem, not the solution, and leave room to learn.