Sprint Zero: a myth, a habit or a useful idea?

By Scrumagic Team Last reviewed 6 min read

In short

Sprint Zero is not in the Scrum Guide, which says all the work needed to achieve the Product Goal happens within Sprints. Teams use the term for setup work before the first real Sprint. The need behind it is real, but the label hides a risk: a period with no Sprint Goal and nothing usable at the end. A better practice is a first Sprint with a thin, working outcome.

A new team gets a new product. There is no repository, no build, no environments, no agreed Definition of Done, and the backlog is a first draft. Someone suggests a Sprint Zero, "just to get set up". Everyone nods, because it sounds sensible. Four weeks later the team has a long list of installed tools and nothing a user could try.

What the Guide says

The Guide has no Sprint Zero. It says all the work necessary to achieve the Product Goal, including Sprint Planning, Daily Scrums, the Sprint Review and the Sprint Retrospective, happens within Sprints. Every Sprint is expected to end with an Increment that is usable and meets the Definition of Done, and every Sprint has a Sprint Goal, which is the single objective for the Sprint.

A Sprint Zero fails each of these. It has no goal that a stakeholder cares about, it produces no Increment and it often skips the events. The Guide's end note is firm on the underlying point: leaving out elements covers up problems.

That said, the Guide does not forbid preparation. The first Sprint is allowed to be about getting started, as long as it is a Sprint, with a Sprint Goal and an Increment. Nothing in the framework stops a team from agreeing on a Definition of Done, setting up a repository, and building the thinnest possible slice in the same Sprint.

What the SBOK does

The SBOK® Guide takes a different structure. It places the Initiate phase before any Sprint: creating the project vision, identifying the Scrum Master and stakeholders, forming the Scrum team, developing epics, creating the Prioritized Product Backlog and conducting release planning. These processes are numbered 8.1 to 8.6 in the Fifth Edition. They happen before the iterative Sprints begin and include creating the Done Criteria and the release planning schedule.

So the SBOK has an explicit pre-Sprint phase, and it is part of the method. It is more like a short project initiation than a Sprint Zero. It involves the Product Owner, stakeholders and the team, and it produces specific outputs. The two sources therefore differ in structure while agreeing that preparation is needed.

A comparable idea outside Scrum is the discovery phase in government digital services. The GOV.UK Service Manual describes a phase in which the team understands the problem before building: users, constraints, opportunities and the value of solving it. It says not to start building the service during discovery, and notes that around four to eight weeks is typical but the purpose should decide how long it takes. That is closer to the SBOK's initiate phase than to a Sprint Zero.

Why teams reach for it

The reasons are understandable.

  • Technical set-up. Repositories, environments, build pipelines and tools take real time.
  • Team formation. New people need to meet, agree a working method and set a Definition of Done.
  • Backlog preparation. The Product Owner needs a first set of items ordered and refined.
  • Architecture. Some early decisions are hard to change.
  • Pressure. A manager wants a plan before anything else.

Each need is valid. What goes wrong is the container. A separate Sprint Zero often runs long, since there is no Sprint Goal to stop it. It produces no feedback, so assumptions go untested. And it invites a Sprint One, Two and Three that all look like Sprint Zero, with "technical Sprints" and "hardening Sprints" that delay value.

A better approach: a thin first slice

This is an illustrative case. A team is building an online booking tool. Rather than a Sprint Zero, the Product Owner and team agree a first Sprint Goal: a person can create an account and book one fixed appointment slot, end to end, on a test environment.

To meet it, the team must do the set-up, because the goal needs a repository, a pipeline, an environment and a working path through the system. The set-up is real, driven by the goal, and only as large as the goal needs. The Increment is ugly and tiny, and it works. At the Review, a stakeholder clicks through it and asks for the confirmation email to say the practitioner's name. The Definition of Done is written in the first planning session, short at first, and tightened in the Retrospective.

The team ends the first Sprint with less set-up than a Sprint Zero would have produced, and with something to inspect. A common name for this kind of slice is a walking skeleton. It is not in either source and is a practitioner idea.

When a short preparation is reasonable

Sometimes a real pre-Sprint period is the honest choice: when a team has not yet been formed, when funding depends on a vision and plan, or when the problem itself is unclear. In those cases do three things.

  1. Call it what it is. "Discovery" or "initiation" is more accurate than Sprint Zero, and sets expectations about what it will deliver.
  2. Timebox it with an outcome. A fixed duration and a stated output, such as a vision, a first ordered backlog and a Definition of Done, stop it from drifting. The SBOK's initiate processes list those outputs.
  3. Keep it short. The longer it runs, the more it resembles waterfall's requirements phase.

A note on hardening and stabilisation Sprints

Sprint Zero has relatives at the other end of a project: the hardening Sprint, the stabilisation Sprint, the release Sprint. They share the same logic. Work that should have met the Definition of Done is pushed into a later period of its own. The Guide's rule that quality does not decrease during the Sprint, and that an item that does not meet the Definition of Done returns to the Product Backlog, leaves no room for them. If a team finds it needs one, the signal is that its Definition of Done is thinner than the work requires, and the repair is to tighten the definition and change the practices, not to add a Sprint.

Common mistakes

  • Treating it as a free Sprint. No goal and no Increment means no inspection.
  • Skipping the events. Even setup work benefits from a Daily Scrum and a Retrospective.
  • Letting Sprint Zero repeat. Sprint Zero, Sprint Zero-and-a-half and then "stabilisation" Sprints are the same pattern.
  • Putting only technical work in it. The Product Owner's preparation matters as much.
  • Refusing to do any preparation. Starting with no repository or agreed standard wastes the first Sprint too.

Two perspectives

The Scrum Guide and SBOK differ here.

Scrum Guide

The Scrum Guide has no Sprint Zero and says all the work needed to achieve the Product Goal happens in Sprints, each with a Sprint Goal and a usable Increment.

SBOK®

The SBOK® Guide places an Initiate phase before Sprints, with processes 8.1 to 8.6 that create the vision, form the team, develop epics, prioritise the backlog and plan releases, so preparation is a designed step in its method.

Same thing, different words

  • Sprint Zero (neither source uses it)
  • Initiate phase (SBOK)

The two sources agree that preparation matters. They disagree on whether it happens inside a Sprint or before the first one.

How to practise it

For your next new product, write a Sprint Goal for the first Sprint that needs the set-up work to be done, and check that a stakeholder could see the result. In the simulator the first phase is spent on the vision, team and backlog before the Sprints start, so you can see the SBOK's approach in practice.

Sources

  1. The 2020 Scrum Guide, Scrum Guides. Read on 14 October 2026.
  2. How the discovery phase works, GOV.UK Service Manual. Read on 14 October 2026.

SBOK® is a registered trademark of its owner. Scrumagic is independent and is not affiliated with the owners of SBOK®.

Share this post Link copied

Nothing opened? This computer may have no email program set up. Write it in Gmail or use the copy button and paste the link into your email.

  • Learn Scrum 7 min read

    Writing a Sprint Goal that survives a bad week

    The Sprint Goal is the single objective for a Sprint. It answers why the Sprint is worth doing, gives the team a reason to work together instead of on separate items, and lets the scope bend while the purpose stays fixed. A good goal says what will be true at the end, can be checked at the Sprint Review, and is smaller than the Product Goal it serves.

  • Learn Scrum 7 min read

    The Sprint: a fixed container for turning ideas into value

    A Sprint is a fixed-length event of one month or less, and every other Scrum event happens inside it. It gives a team a regular rhythm of planning, building, inspecting and adapting. Its length is the team's first big planning decision, and the main rule is that the Sprint Goal is not endangered once it starts.

  • Learn Scrum 7 min read

    Sprint Planning: purpose and structure

    Sprint Planning is the event that starts a Sprint. The whole Scrum Team agrees why the Sprint is valuable, what can be finished in it, and how the chosen work will get done. It ends with a Sprint Backlog: a goal, the items chosen to serve it, and a plan the Developers can follow.

  • Learn Scrum 6 min read

    Daily Scrum without the status-meeting trap

    The Daily Scrum is a 15-minute event for the Developers to inspect progress towards the Sprint Goal and adjust the plan for the next day. It turns into a status report when it is aimed at a manager instead of at the work. This post shows what the Scrum Guide actually requires and how to keep the event useful.

  • Learn Scrum 6 min read

    The Sprint Review is not a demo

    The Sprint Review is a working session where the Scrum Team and key stakeholders inspect what was achieved and decide what to do next. Showing the work is part of it, but the purpose is to decide, using the product as evidence. A review that is only a presentation wastes the one regular chance to change direction with the people who matter.